jtt config calendar#

Set the working day and week used to convert between hours, days and weeks.

jtt config calendar --hours-per-day 7.5, then a report in days

$ jtt config calendar --hours-per-day 7.5
$ jtt calculate -p OPS --from 2026-09-21 --to 2026-09-28 --as days

jtt login reads them from the site’s time tracking settings (8 hours a day and 5 days a week, unless your Jira admin changed them). Set them when your team counts days differently from the site. Points are never converted.

Options#

jtt config calendar [OPTIONS]

Option

Default

Description

--hours-per-day FLOAT

Working hours in a day. From 0.5 to 24.

--days-per-week FLOAT

Working days in a week. From 0.5 to 7.

-h, --help

Show the command’s help and exit.